Paldiski-ehitusesThe Paldiski wind farm was completed in October 2012.

There are 9 wind turbines, each with a capacity of 2.5 MW, in the Paldiski wind farm. The total capacity of the wind farm is 22.5 MW and the prognosed yearly production 67 GWh.

The GE Wind Energy electric turbines are produced by a Germany located turbines manufacturing branch of an American large consolidated company GE. The height of the mast of the wind turbine is 85 meters, and rotor diameter is 100 meters. The wind turbine weighs 309 tons. The expected life-span of the wind turbines is 20 years.

The Paldiski wind farm is located in Harju County, on the territory of the town of Paldiski. The wind farm comprises an area of approximately 125 hectares.

A specific project company, Pakri Tuulepargid OÜ, was established for the Paldiski wind farm.

201220132014201520162017
Yearly production (MWh)14 54951 49647 96255 45740 11253 521