Aseriaru wind farm

Construction of the Aseriaru wind farm was started in 2010.

A total of 8 WinWinD WWD3/100 type wind turbines will be erected, each with a capacity of 3 MW, in the Aseriaru wind farm. The total capacity of the wind farm will be 24 MW and the yearly production of electricity will be approximately 71 GWh.

The electric turbines are produced by the Finnish company, Winwind Oy. The height of the mast of the wind turbine is 90 m, and rotor diameter is 100 m. The wind turbine weighs 305 tons. The expected life-span of the wind turbines is 20 years.

The Aseriaru wind farm is located in Ida-Viru County, Aseri Rural Municipality, between the Tallinn-Narva Highway and the Aseri urban area. The wind farm comprises an area of approximately 200 hectares.

View Aseriaru wind park’s planned location in Google Earth.